QUEST In which of the following scope management processes is the scope management plan prepared?
A Initiation
B Scope planning
C Scope Definition
D Scope change control
E Scope verification
参考答案:B

QUEST The project charter is prepared in which scope management process?
A Initiation
B Scope planning
C Scope Definition
D Scope change control
E Scope verification
参考答案:A

QUEST The work breakdown structure (WBS) is first developed in which scope management process?
A Initiation
B Scope planning
C Scope change control
D Scope Definition
E Scope verification
参考答案:D

QUEST In which of the following scope management processes are subject matter experts used?
A Initiation
B Scope planning
C Scope Definition
D Scope change control
E Scope verification
参考答案:A

QUEST A Work Berakdown Structure is most useful for:
A Identifying individual tasks for a project.
B Scheduling the start of tasks.
C Developing a cost estimate.
D Determining potential delays.
E A and C.
参考答案:E