QUEST Work packages are used to:
A Represent units of work at a level where work is performed.
B Clearly distinguish one work package from all others assigned to a single functional group.
C Limit the work to be performed to relatively short periods of time.
D All of the above.
E A and B only
参考答案:D
QUEST Project life cycles are very useful for _____ and _____ .
A Configuration management, termination
B Objective setting, information gathering
C Standardization, control
D Configuration management, weekly status updates
E Approval, termination
参考答案:C
QUEST Which of the following are included as part of a scope statement?
A Project justification
B Project deliverables
C Project objectives
D All of the above
E B and C
参考答案:D
QUEST The initial document that formally recognizes the existence of a project is the _____ .
A Scope baseline
B Management plan
C Project charter
D Configuration control report
E None of the above
参考答案:C
QUEST Which of the following is not a scope management process?
A Initiation
B Scope planning
C Scope Definition
D Scope change control
E Scope verification
参考答案:D